2016-04-21 / Front Page

Broadway Construction Updates For This Week

This week, weather permitting, RIDOT anticipates finishing the installation of the parking pavers, from Equality Park to Caleb Earl Street. Work will also begin on parking area excavation from Caleb Earl Street to Oak Street. Installation of the large planters is scheduled for completion between Oak Street and Collins Street. Curbing and sidewalk will be installed in this area.

RIDOT also anticipates curbing and sidewalk installation from Oak Street to Marlborough Street. Local businesses from Collins Street to Marlborough Street should see sidewalk placement beginning on Wednesday. Parking will be limited on a day to day basis from Collins Street to Marlborough Street as the activity in this area increases.