2015-07-16 / Around Town

Broadway Phase Two

At the end of May the top layer of pavement on the east side of Broadway was removed beginning at Courthouse Way near the Fastnet Pub. That first phase of the Broadway Streetscape Project was completed on July 10 with new sidewalks, curbing and fresh asphalt. Construction moved north on July 15 with digging in front of Thompson Middle School and City Hall. Each 600-foot segment of the street will take from 45 to 60 days to complete, taking the project to Equality Park by the end of this year. Construction will then “turn” to head back south in similar 600- foot increments on the west side of Broadway. The tentative date for completion is scheduled for October of 2016. (Photo by Nila Asciolla)